The Path To 450+ Truckloads Per Day For Atlas Sand [Chart Of The Day]

About one week ago, the first truckload of finished frac sand left Atlas Sand’s gate in Kermit. Since then, the company has been ramping up shipments fast at this facility. Shipping milestones from the plant’s first week give us more confidence in management’s projected six-week timeline to achieve full production.. Read More

Source:

INFILL THINKING BY JOSEPH TRIEPKE